Big Tech Energy Deals
Every major nuclear, fusion and clean power deal by Amazon, Google, Meta and Microsoft: megawatts, partner, site, term and when the power arrives.
- Capacity announced in tracked deals
- 56.6 GW
- headline figures, incl. targets
- Of which nuclear
- 33.8 GW
- existing, restarted and new reactors
- Natural gas for data centers
- 7.2 GW
- Microsoft, Oracle, Meta
- Largest single deal
- 12 GW
- Switch and Oklo, non-binding master agreement
Who is buying, and what
By buyer (GW)
By technology (GW)
Deals by technology
Every tracked deal
Newest first. MW as announced. Filter by buyer or technology.
29 rows
| Announced | Buyer | Partner | Technology | MW | Where | Term | Power from | Source |
|---|---|---|---|---|---|---|---|---|
| Constellation Our story | Nuclear (uprates at 11 units) | 890 | Illinois, Pennsylvania, New Jersey | 20 years | First uprate 2028 | constellationenergy.com (opens in a new tab) | ||
| Amazon | Constellation Our story | Nuclear (existing plant, uprate) | 690 | Calvert Cliffs, Maryland | 20 years | Uprate 2030 to 2032 | constellationenergy.com (opens in a new tab) | |
| Microsoft | Chevron | Natural gas (new plant) | 2,670 | Project Kilby, West Texas | 20 years | 2028 | chevroncorp.gcs-web.com (opens in a new tab) | |
| Meta | Vistra, TerraPower, Oklo | Nuclear (existing, new reactors) | 6,600 | Ohio and other US sites | Up to 20 years | By 2035 | about.fb.com (opens in a new tab) | |
| Intersect | Acquisition (energy developer) | n/a | US | Acquisition | Closed March 2026 | abc.xyz (opens in a new tab) | ||
| NextEra Energy | Data center campuses with own generation | n/a | US, first three campuses not named | Partnership | Not stated | newsroom.nexteraenergy.com (opens in a new tab) | ||
| NextEra Energy | Nuclear (restart) | 615 | Duane Arnold, Iowa | 25 years | Targeted Q1 2029 | investor.nexteraenergy.com (opens in a new tab) | ||
| Meta | ENGIE | Renewables (solar) | 600 | Swenson Ranch, Stonewall County, Texas | PPA | 2027 | engie-na.com (opens in a new tab) | |
| Oracle | VoltaGrid | Natural gas (modular) | 2,300 | Texas | Not stated | Not stated | voltagrid.com (opens in a new tab) | |
| Meta | Entergy Louisiana | Natural gas (new plants) | 2,262 | Hyperion data center, Richland Parish, Louisiana | Regulator approval | Late 2028 and 2029 | entergy.com (opens in a new tab) | |
| Kairos Power, TVA | Advanced nuclear (Gen IV) | 50 | Hermes 2, Oak Ridge, Tennessee | Not stated | 2030 | blog.google (opens in a new tab) | ||
| Brookfield | Hydropower | 3,000 | Holtwood and Safe Harbor, Pennsylvania, and other US sites | Framework; first PPAs 20 years | Not stated | bam.brookfield.com (opens in a new tab) | ||
| Commonwealth Fusion Systems | Fusion | 200 | ARC, Chesterfield County, Virginia | Not stated | Early 2030s (planned) | blog.google (opens in a new tab) | ||
| Meta | Invenergy | Renewables (wind, solar) | 791 | Ohio, Arkansas, Texas | PPAs | 2027 and 2028 | invenergy.com (opens in a new tab) | |
| Meta | XGS Energy | Geothermal (advanced) | 150 | New Mexico | Not stated | By 2030 | xgsenergy.com (opens in a new tab) | |
| Amazon | Talen Energy | Nuclear (existing plant) | 1,920 | Susquehanna, Pennsylvania | 17 years | Ramps to full volume by 2032 | sec.gov (opens in a new tab) | |
| Meta | Constellation Our story | Nuclear (existing plant) | 1,121 | Clinton, Illinois | 20 years | June 2027 | constellationenergy.com (opens in a new tab) | |
| Elementl Power | Advanced nuclear (site development) | 1,800 | Three US sites, not named | Development capital, offtake option | Not stated | elementlpower.io (opens in a new tab) | ||
| Switch | Oklo | Advanced nuclear (new reactors) | 12,000 | US | Non-binding master agreement | Through 2044 | oklo.com (opens in a new tab) | |
| Amazon | X-energy | Small modular reactors | 5,000 | Washington state and other US sites | Target, not a PPA | By 2039 | x-energy.com (opens in a new tab) | |
| Amazon | Dominion Energy | Small modular reactors (explore) | 300 | North Anna, Virginia | Memorandum of understanding | Not stated | news.dominionenergy.com (opens in a new tab) | |
| Kairos Power | Small modular reactors | 500 | US, sites not named | Fleet agreement | First reactor by 2030, more through 2035 | blog.google (opens in a new tab) | ||
| Microsoft | Constellation Our story | Nuclear (restart) | 835 | Crane (Three Mile Island Unit 1), Pennsylvania | 20 years | Restart planned | constellationenergy.com (opens in a new tab) | |
| Meta | Sage Geosystems | Geothermal (advanced) | 150 | East of the Rocky Mountains | Not stated | First phase 2027 | about.fb.com (opens in a new tab) | |
| NV Energy, Fervo Energy | Geothermal (enhanced) | 115 | Corsac Station, Nevada | Clean Transition Tariff | Approved May 2025 | blog.google (opens in a new tab) | ||
| Microsoft | Brookfield | Renewables (wind, solar) | 10,500 | US and Europe | Framework, 2026 to 2030 | 2026 | bep.brookfield.com (opens in a new tab) | |
| Equinix | Oklo | Advanced nuclear (new reactors) | 500 | US | Pre-agreement, 20-year PPAs | Not stated | sec.gov (opens in a new tab) | |
| Amazon | Talen Energy | Nuclear (campus purchase) | 960 | Cumulus campus at Susquehanna, Pennsylvania | Campus sale plus PPA | 2024 | ir.talenenergy.com (opens in a new tab) | |
| Microsoft | Helion | Fusion | 50 | Washington state | PPA | Plant targeted 2028 | helionenergy.com (opens in a new tab) |
Deal timeline
Google and Constellation: 890 MW, nuclear (uprates at 11 units)
Constellation plans to invest about $4.3 billion in the uprates.
Amazon and Constellation: 690 MW, nuclear (existing plant, uprate)
690 MW including a 190 MW uprate; power stays on the PJM grid.
Microsoft and Chevron: 2,670 MW, natural gas (new plant)
Co-located gas power plant of about 2.67 GW for a Microsoft data center.
Meta and Vistra, TerraPower, Oklo: 6,600 MW, nuclear (existing, new reactors)
Up to 6.6 GW of new and existing nuclear capacity across three agreements.
Google and Intersect: acquisition (energy developer)
Alphabet agreed to buy the data center and energy developer for $4.75 billion in cash plus assumed debt.
Google and NextEra Energy: data center campuses with own generation
Joint development of gigawatt-scale data center campuses with dedicated generation.
Google and NextEra Energy: 615 MW, nuclear (restart)
Restart of Iowa's only nuclear plant.
Meta and ENGIE: 600 MW, renewables (solar)
New 600 MW solar project takes ENGIE contracts with Meta to more than 1.3 GW.
Oracle and VoltaGrid: 2,300 MW, natural gas (modular)
2.3 GW of modular natural gas power for Oracle Cloud Infrastructure AI data centers.
Meta and Entergy Louisiana: 2,262 MW, natural gas (new plants)
Louisiana regulators approved three combined-cycle gas plants to serve the Meta data center.
Google and Kairos Power, TVA: 50 MW, advanced nuclear (gen iv)
First purchase of power from a Gen IV reactor by a US utility.
Google and Brookfield: 3,000 MW, hydropower
Framework for up to 3,000 MW; first contracts cover 670 MW and more than $3 billion.
Google and Commonwealth Fusion Systems: 200 MW, fusion
Largest direct corporate offtake agreement for fusion power, per Google.
Meta and Invenergy: 791 MW, renewables (wind, solar)
Four solar and wind projects totalling 791 MW.
Meta and XGS Energy: 150 MW, geothermal (advanced)
Closed-loop geothermal project on the PNM grid, built in two phases.
Amazon and Talen Energy: 1,920 MW, nuclear (existing plant)
About $18 billion over the contract, per Talen.
Meta and Constellation: 1,121 MW, nuclear (existing plant)
Supports relicensing; adds 30 MW through uprates.
Google and Elementl Power: 1,800 MW, advanced nuclear (site development)
Three sites of at least 600 MW each; Google has an option to buy the power.
Switch and Oklo: 12,000 MW, advanced nuclear (new reactors)
12 GW of Oklo Aurora powerhouses, with binding PPAs as milestones are met.
Amazon and X-energy: 5,000 MW, small modular reactors
Goal of more than 5 GW of SMRs; Amazon co-led a $500M round in X-energy.
Amazon and Dominion Energy: 300 MW, small modular reactors (explore)
Agreement to explore an SMR of at least 300 MW near North Anna; not a commitment to build.
Google and Kairos Power: 500 MW, small modular reactors
Up to 500 MW of new 24/7 carbon-free power.
Microsoft and Constellation: 835 MW, nuclear (restart)
Constellation's largest-ever power purchase agreement.
Meta and Sage Geosystems: 150 MW, geothermal (advanced)
Up to 150 MW of geopressured geothermal power.
Google and NV Energy, Fervo Energy: 115 MW, geothermal (enhanced)
Utility tariff that supplies Google with 115 MW of enhanced geothermal power.
Microsoft and Brookfield: 10,500 MW, renewables (wind, solar)
Framework for over 10.5 GW of new renewable capacity.
Equinix and Oklo: 500 MW, advanced nuclear (new reactors)
Up to 500 MW with a $25 million prepayment.
Amazon and Talen Energy: 960 MW, nuclear (campus purchase)
AWS bought the 960 MW data center campus next to the Susquehanna plant for $650 million.
Microsoft and Helion: 50 MW, fusion
First fusion power purchase agreement; at least 50 MW after a one-year ramp.
Methodology
One row per announced agreement between a large AI company and a power producer or developer, sourced to the press release or a trade publication that quotes it. Capacity is the headline megawatt figure as announced. Targets and frameworks are marked in the Term column.
Limits. Headline capacity is not delivered power: many projects are years away, and targets may not be met. We list deals of 50 MW or more by the four largest US cloud and AI spenders.
Data note. Capacity is the headline figure each company announced. Targets, frameworks and non-binding agreements (for example Switch and Oklo, Amazon and X-energy, Microsoft and Brookfield, Meta's 6.6 GW) are upper bounds, not contracted output, and are labelled in the Term column. Two Google deals (Intersect, NextEra campuses) state no capacity and are left out of the totals. Switch and Equinix are data center operators, not Big Tech, and are included because their deals are among the largest.
All 29 sources
- https://www.constellationenergy.com/news/2026/10/google-and-constellation-announce-landmark-agreement-to-bring-890-mw-of-new-nuclear-capacity-to-pjm-grid.html (opens in a new tab)
- https://www.constellationenergy.com/news/2026/09/constellation-and-amazon-announce-20-year-power-purchase-agreement-at-calvert-cliffs.html (opens in a new tab)
- https://chevroncorp.gcs-web.com/news-releases/news-release-details/chevron-signs-20-year-power-agreement-microsoft-west-texas-data (opens in a new tab)
- https://about.fb.com/news/2026/01/meta-nuclear-energy-projects-power-american-ai-leadership/ (opens in a new tab)
- https://abc.xyz/investor/news/news-details/2025/Alphabet-Announces-Agreement-to-Acquire-Intersect-to-Advance-U-S–Energy-Innovation-2025-DVIuVDM9wW/ (opens in a new tab)
- https://newsroom.nexteraenergy.com/2025-12-08-NextEra-Energy-and-Google-Cloud-Announce-Landmark-Strategic-Energy-and-Technology-Partnership-to-Accelerate-AI-Growth-and-Transform-the-Energy-Industry (opens in a new tab)
- https://www.investor.nexteraenergy.com/news-and-events/news-releases/2025/10-27-2025-203948689 (opens in a new tab)
- https://www.engie-na.com/engie-and-meta-expand-ppa-to-more-than-1-3-gw/ (opens in a new tab)
- https://voltagrid.com/voltagrid-collaborates-with-oracle-to-power-next-gen-ai-data-centers (opens in a new tab)
- https://www.entergy.com/news/entergy-louisiana-receives-lpsc-approval-for-major-infrastructure-investments-to-support-metas-data-center-and-improve-reliability (opens in a new tab)
- https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/ (opens in a new tab)
- https://bam.brookfield.com/press-releases/brookfield-and-google-sign-hydro-framework-agreement-deliver-3000-mw-homegrown (opens in a new tab)
- https://blog.google/company-news/outreach-and-initiatives/sustainability/our-latest-bet-on-a-fusion-powered-future/ (opens in a new tab)
- https://invenergy.com/2025/06/26/invenergy-to-provide-meta-with-nearly-800-mw-supporting-data-center-operations/ (opens in a new tab)
- https://www.xgsenergy.com/xgs-energy-and-meta-to-partner-on-150-mw-advanced-geothermal-project/ (opens in a new tab)
- https://www.sec.gov/Archives/edgar/data/1622536/000162828025030559/a20250611pressreleasebusin.htm (opens in a new tab)
- https://www.constellationenergy.com/news/2025/constellation-meta-sign-20-year-deal-for-clean-reliable-nuclear-energy-in-illinois.html (opens in a new tab)
- https://www.elementlpower.io/newsroom/050725/google (opens in a new tab)
- https://oklo.com/newsroom/oklo-and-switch-form-landmark-strategic-relationship-to-deploy-12-gigawatts-of-advanced-nuclear- (opens in a new tab)
- https://x-energy.com/news/amazon-invests-in-x-energy-to-support-advanced-small-modular-nuclear-reactors-and-expand-carbon-free-power/ (opens in a new tab)
- https://news.dominionenergy.com/press-releases/press-releases/2024/Dominion-Energy-and-Amazon-to-explore-advancement-of-Small-Modular-Reactor-SMR-nuclear-development-in-Virginia-10-16-2024/default.aspx (opens in a new tab)
- https://blog.google/outreach-initiatives/sustainability/google-kairos-power-nuclear-energy-agreement/ (opens in a new tab)
- https://www.constellationenergy.com/newsroom/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-Restoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html (opens in a new tab)
- https://about.fb.com/news/2024/08/new-geothermal-energy-project-to-support-our-data-centers/ (opens in a new tab)
- https://blog.google/company-news/outreach-and-initiatives/sustainability/google-clean-energy-partnership/ (opens in a new tab)
- https://bep.brookfield.com/press-releases/bep/brookfield-and-microsoft-collaborating-deliver-over-105-gw-new-renewable-power (opens in a new tab)
- https://www.sec.gov/Archives/edgar/data/1849056/000110465924047344/tm2324337d21_ex10-19.htm (opens in a new tab)
- https://ir.talenenergy.com/news-releases/news-release-details/talen-energy-announces-sale-zero-carbon-data-center-campus (opens in a new tab)
- https://www.helionenergy.com/articles/helion-announces-worlds-first-fusion-ppa-with-microsoft/ (opens in a new tab)
Spotted an error or a missing row? Write to the newsroom via Contact. We correct and date every change.
How to cite or embed
Free to quote, chart and embed. Please credit i10X News and link to this page.
More from the data desk
- IndexAI Funding IndexMonthly AI venture totals and every tracked round, by country, sector and stage.
- TrackerHumanoid Robot Price TrackerWhat each humanoid robot costs, whether you can buy it, and what it can actually do.
- TrackerFDA AI Medical Device TrackerEvery AI-enabled medical device the FDA has authorized, by year, specialty and company.
- MeterAI Energy MeterHow much electricity data centres and AI prompts use, from official and company sources.
- TrackerAI Capex TrackerWhat Amazon, Alphabet, Microsoft, Meta, Oracle and CoreWeave spend each quarter, from SEC filings.
- TrackerAI in Education Policy TrackerWhich countries and states teach AI, give students AI tools, or set rules for schools.
- ScoreHype vs. Reality ScoreBig AI promises checked 3, 6 and 12 months later. Did they ship?
- TrackerAI Stocks TrackerMarket value of 30 listed AI chip, cloud, software and power companies, from exchange data.
- ListAI Unicorns ListAI startups valued at $1 billion or more in rounds we verified, sortable by valuation and sector.
- ComparisonRobot AI Model ComparisonGemini Robotics, GR00T, π, Helix and other robot foundation models side by side.
- ComparisonAI Tools for Education ComparedChatGPT Edu, Gemini for Education, Claude for Education, Copilot and Khanmigo: price, data terms, features.
- ComparisonAI Country ComparisonCompare countries on private AI investment, new AI companies, AI talent and AI law.
- BarometerX Conversation BarometerHow many posts on X talk about AI funding, robots, data centre power, jobs and more, day by day.
- ReportState of AI in Startups, Q4 2026Quarterly report: the key numbers from every Startups tracker in one page.
- ReportState of AI in Health & Medical Research, Q4 2026Quarterly report: the key numbers from every Health & Medical Research tracker in one page.
- ReportState of AI in Engineering & Robotics, Q4 2026Quarterly report: the key numbers from every Engineering & Robotics tracker in one page.
- ReportState of AI in Finance, Q4 2026Quarterly report: the key numbers from every Finance tracker in one page.
- ReportState of AI in Education, Q4 2026Quarterly report: the key numbers from every Education tracker in one page.
- ReportState of AI in Climate & Energy, Q4 2026Quarterly report: the key numbers from every Climate & Energy tracker in one page.
- TrackerAI M&A TrackerEvery AI acquisition, acqui-hire and licensing deal we verified, with price where stated.
- ListAI Startup GraveyardAI startups that shut down, sold for parts or folded into Big Tech, and what happened.
- BarometerAI Jobs BarometerHow many job ads ask for AI skills, and which job categories are being advertised less.
- CalculatorAI ROI CalculatorEstimate hours and money saved with AI tools, using effect sizes from published studies.
- ListBanks Using AIWhich banks use generative AI, for what, and with which vendor, from bank announcements.