AI Energy Meter

How much electricity AI and data centres use: IEA and US DOE figures, grid shares, and what one AI prompt costs in energy according to Google and OpenAI.

Updated November 16, 202699 sourced rows, 64 map featuresEvery row sourcedMethodologyCite or embed

World data centres, 2025
485 TWh
up 17% on 2024, iea.org (opens in a new tab)
AI-focused data centres, 2025
155 TWh
up 50% in a year, iea.org (opens in a new tab)
Projected for 2030
950 TWh
about 3% of world electricity, iea.org (opens in a new tab)
US data centres, 2023
4.4%
176 TWh, up to 12% by 2028, energy.gov (opens in a new tab)
Ireland, 2025
23%
of metered electricity, cso.ie (opens in a new tab)
Virginia, 2023
25.6%
of state electricity, highest in the US, restservice.epri.com (opens in a new tab)

Where data centres use the most electricity

Shade shows the data centre share of electricity where an official figure exists. Select a country, state or dot for the figure, year and source.

  • Official figure, no share
  • 2%+
  • 4%+
  • 10%+
  • 20%+
  • AI campus (size by announced MW)

Select a highlighted area or a dot to see the figure and its source.

Forecast to 2030 and 2035

World data centres, TWh (2030 and 2035 are IEA projections)

IEA estimates for 2024 and 2025, Base Case projections for 2030 and 2035. Download chart (SVG)

Data centres compared with whole countries

National figures are total electricity generation from Ember, used as a size reference. Data centre figures are consumption.

World data centres vs national electricity generation, 2025, TWh

  1. Japan1,027
  2. France574
  3. Germany497
  4. All data centres485
  5. Saudi Arabia471
  6. Mexico390
  7. United Kingdom294
  8. Spain288
  9. Australia286
  10. Italy265
Download chart (SVG)

Per-prompt disclosures

Model and unitWhWater mLg CO2eWhat it coversSource
Google Gemini Apps, median text prompt0.240.260.03Comprehensive: active accelerators, host CPU and RAM, idle capacity and data centre overhead (PUE). May 2025 measurement.cloud.google.com (opens in a new tab)
Google Gemini Apps, active machine only0.1n/an/aNarrow method that counts only active TPU and GPU use. Google publishes it to show how method changes the number.cloud.google.com (opens in a new tab)
ChatGPT, average query0.340.32n/aStated by OpenAI CEO Sam Altman in June 2025 (0.000085 gallons of water). No method published.blog.samaltman.com (opens in a new tab)
Mistral Large 2, 400-token responsen/a451.14Life-cycle analysis with ADEME and Carbone 4, includes training and hardware share. Energy per response not published.mistral.ai (opens in a new tab)

Power mix of data centres today

IEA estimate of the electricity supplying data centres worldwide (2024). Other is the remainder to 100.

  • Coal 30%
  • Renewables 27%
  • Natural gas 26%
  • Nuclear 15%
  • Other 2%

Where the new power comes from

The IEA expects generation supplying data centres to grow from 460 TWh in 2024 to more than 1,000 TWh in 2030 and 1,300 TWh in 2035. Renewables meet nearly half of the extra demand, and natural gas adds about 175 TWh by 2035. Big tech is also signing nuclear and clean power contracts directly: see every deal in our Big Tech Energy Deals tracker.

National time series

Ireland, data centres as % of metered electricity

Download chart (SVG)

US states

Top US states by data centre share of electricity, 2023

  1. Virginia25.6%
  2. North Dakota15.4%
  3. Nebraska11.7%
  4. Iowa11.4%
  5. Oregon11.4%
  6. Wyoming11.3%
  7. Nevada8.7%
  8. Utah7.7%
  9. Arizona7.4%
  10. Washington5.7%
Download chart (SVG)

Big tech electricity use

As reported in each company sustainability report. Google reports data centres only; Microsoft and Meta report company totals, which are mostly data centres.

Google, Data centre electricity (TWh)

Download chart (SVG)

Water

Only officially reported figures. Scopes differ: Google and Meta report data centres, Microsoft reports the whole company.

Microsoft total water consumption, megalitres

Download chart (SVG)

Reported water consumption

CompanyMeasureReportedUnitMegalitresSource
GoogleData centre water consumption, 202510,523million gallons39,834sustainability.google (opens in a new tab)
MicrosoftTotal water consumption, FY258,170megalitres8,170cdn-dynmedia-1.microsoft.com (opens in a new tab)
MetaData centre water consumption, 20242,974megalitres2,974sustainability.atmeta.com (opens in a new tab)

Countries

CountryTWhShare %YearNoteSource
United States1764.4%2023LBNL for US DOE. IEA puts the US at 45% of the world total in 2024.energy.gov (opens in a new tab)
Chinan/an/a2024About 25% of the world total of 415 TWh in 2024 (IEA). IEA sees an increase of about 175 TWh by 2030.iea.org (opens in a new tab)
Japann/an/a2024IEA expects Japan to add about 15 TWh by 2030 (up 80%). OCCTO projects 49.4 TWh of new data centre demand by fiscal 2035.iea.org (opens in a new tab)
Germany204%2024Data centres and smaller IT installations. 31 TWh expected in 2030 (BMWK study).bundeswirtschaftsministerium.de (opens in a new tab)
Ireland7.66323%2025Metered consumption, up from 5% in 2015. Highest share of any country we track.cso.ie (opens in a new tab)
Netherlands5.14.6%2024Provisional. Share rose from 1.5% in 2017.cbs.nl (opens in a new tab)
United Kingdom4.52%2024Great Britain, grid electricity; excludes enterprise data centres. 77% in London and the South East.assets.publishing.service.gov.uk (opens in a new tab)
Norway3.3n/a2025Doubled since 2023 (NVE).nve.no (opens in a new tab)
Singaporen/a7%20247% of national electricity, stated by the Senior Minister of State in May 2024. Capacity above 1.4 GW (IMDA).mddi.gov.sg (opens in a new tab)
Denmarkn/an/a2030Energistyrelsen assumes 1,240 MW of grid capacity for data centres by 2030 (AF23).ens.dk (opens in a new tab)

All US states with EPRI figures

43 rows

StateTWh, 2023Share of state electricity, %Source
Virginia33.85125.59restservice.epri.com (opens in a new tab)
Texas21.8134.59restservice.epri.com (opens in a new tab)
California9.3323.7restservice.epri.com (opens in a new tab)
Illinois7.455.48restservice.epri.com (opens in a new tab)
Oregon6.41411.39restservice.epri.com (opens in a new tab)
Arizona6.2537.43restservice.epri.com (opens in a new tab)
Iowa6.19311.43restservice.epri.com (opens in a new tab)
Georgia6.1754.26restservice.epri.com (opens in a new tab)
Washington5.1725.69restservice.epri.com (opens in a new tab)
Pennsylvania4.593.16restservice.epri.com (opens in a new tab)
New York4.0672.84restservice.epri.com (opens in a new tab)
New Jersey4.0385.42restservice.epri.com (opens in a new tab)
Nebraska3.9611.7restservice.epri.com (opens in a new tab)
North Dakota3.91615.42restservice.epri.com (opens in a new tab)
Nevada3.4178.69restservice.epri.com (opens in a new tab)
North Carolina2.6731.92restservice.epri.com (opens in a new tab)
Utah2.5627.68restservice.epri.com (opens in a new tab)
Ohio2.3641.58restservice.epri.com (opens in a new tab)
South Carolina2.0242.45restservice.epri.com (opens in a new tab)
Wyoming1.85711.26restservice.epri.com (opens in a new tab)
Kentucky1.6212.15restservice.epri.com (opens in a new tab)
Colorado1.512.66restservice.epri.com (opens in a new tab)
Florida1.3840.56restservice.epri.com (opens in a new tab)
Tennessee1.3271.3restservice.epri.com (opens in a new tab)
Oklahoma1.2261.76restservice.epri.com (opens in a new tab)
Massachusetts1.0622.08restservice.epri.com (opens in a new tab)
Missouri0.9721.21restservice.epri.com (opens in a new tab)
Minnesota0.8241.24restservice.epri.com (opens in a new tab)
Montana0.5783.71restservice.epri.com (opens in a new tab)
Michigan0.5260.52restservice.epri.com (opens in a new tab)
New Mexico0.4031.48restservice.epri.com (opens in a new tab)
Connecticut0.2630.95restservice.epri.com (opens in a new tab)
Indiana0.1930.19restservice.epri.com (opens in a new tab)
Idaho0.1490.57restservice.epri.com (opens in a new tab)
Wisconsin0.1490.21restservice.epri.com (opens in a new tab)
Maryland0.0960.16restservice.epri.com (opens in a new tab)
Louisiana0.0790.08restservice.epri.com (opens in a new tab)
South Dakota0.070.52restservice.epri.com (opens in a new tab)
Maine0.0260.22restservice.epri.com (opens in a new tab)
New Hampshire0.0180.16restservice.epri.com (opens in a new tab)
Rhode Island0.0180.23restservice.epri.com (opens in a new tab)
Hawaii0.0090.1restservice.epri.com (opens in a new tab)
Kansas0.0090.02restservice.epri.com (opens in a new tab)

AI campuses

Sizes as announced by the operators. Three rows rely on press reports and are marked Secondary.

11 rows

CampusOperatorLocationMWSize as announcedStatusSource
Stargate AbileneOpenAI, Oracle, CrusoeAbilene, Texasn/aFlagship Stargate site; part of nearly 7 GW planned across Stargate sitesOperating, expandingopenai.com (opens in a new tab)
Stargate Shackelford CountyOpenAI, OracleShackelford County, Texasn/aOracle-developed sites together over 5.5 GWAnnounced Sep 2025openai.com (opens in a new tab)
Stargate Doña Ana CountyOpenAI, OracleDoña Ana County, New Mexicon/aOracle-developed sites together over 5.5 GWAnnounced Sep 2025openai.com (opens in a new tab)
Stargate LordstownOpenAI, SoftBankLordstown, Ohion/aSoftBank sites together up to 1.5 GWAnnounced Sep 2025openai.com (opens in a new tab)
Stargate Milam CountyOpenAI, SoftBank, SB EnergyMilam County, Texasn/aSoftBank sites together up to 1.5 GWAnnounced Sep 2025openai.com (opens in a new tab)
HyperionMetaRichland Parish, Louisiana5,000Designed to scale to 5 GW over several yearsUnder constructiontechcrunch.com (opens in a new tab) Secondary
PrometheusMetaNew Albany, Ohio1,0001 GW cluster, expected online in 2026Coming online 2026techcrunch.com (opens in a new tab) Secondary
ColossusxAIMemphis, Tennesseen/a200,000 H100 GPUs in one cluster, roadmap to 1 million GPUs; power not stated on the pageOperatingx.ai (opens in a new tab)
FairwaterMicrosoftMount Pleasant, Wisconsinn/a315 acres, three buildings, 1.2 million sq ft; power not statedOperating 2026blogs.microsoft.com (opens in a new tab)
Fairwater AtlantaMicrosoftAtlanta, Georgian/aSecond Fairwater site, linked to Wisconsin by an AI WANOperatingblogs.microsoft.com (opens in a new tab)
Project RainierAmazon (for Anthropic)New Carlisle, Indiana2,200More than 2.2 GW at full build, 1,200 acresOperating, expandingcnbc.com (opens in a new tab) Secondary

Forecast figures

12 rows

AreaYearTWhTypeSource
World2024415Estimateiea.org (opens in a new tab)
World2025485Estimateiea.org (opens in a new tab)
World2030945IEA Base Case (2025 report)iea.org (opens in a new tab)
World2030950IEA projection (2026 update)iea.org (opens in a new tab)
World2035700Headwinds caseiea.org (opens in a new tab)
World2035970High Efficiency caseiea.org (opens in a new tab)
World20351,200Base Caseiea.org (opens in a new tab)
World20351,700Lift-Off case (more than)iea.org (opens in a new tab)
United States201458Estimateenergy.gov (opens in a new tab)
United States2023176Estimateenergy.gov (opens in a new tab)
United States2028325LBNL low scenarioenergy.gov (opens in a new tab)
United States2028580LBNL high scenarioenergy.gov (opens in a new tab)

Company electricity series

16 rows

CompanyMeasurePeriodTWhSource
GoogleData centre electricity (TWh)202117.4sustainability.google (opens in a new tab)
GoogleData centre electricity (TWh)202220.6sustainability.google (opens in a new tab)
GoogleData centre electricity (TWh)202324sustainability.google (opens in a new tab)
GoogleData centre electricity (TWh)202430.6sustainability.google (opens in a new tab)
GoogleData centre electricity (TWh)202542.4sustainability.google (opens in a new tab)
MicrosoftTotal electricity (TWh, fiscal years)FY2010.8cdn-dynmedia-1.microsoft.com (opens in a new tab)
MicrosoftTotal electricity (TWh, fiscal years)FY2113.6cdn-dynmedia-1.microsoft.com (opens in a new tab)
MicrosoftTotal electricity (TWh, fiscal years)FY2218.2cdn-dynmedia-1.microsoft.com (opens in a new tab)
MicrosoftTotal electricity (TWh, fiscal years)FY2323.6cdn-dynmedia-1.microsoft.com (opens in a new tab)
MicrosoftTotal electricity (TWh, fiscal years)FY2429.8cdn-dynmedia-1.microsoft.com (opens in a new tab)
MicrosoftTotal electricity (TWh, fiscal years)FY2537cdn-dynmedia-1.microsoft.com (opens in a new tab)
MetaTotal electricity (TWh)20207.2sustainability.atmeta.com (opens in a new tab)
MetaTotal electricity (TWh)20219.4sustainability.atmeta.com (opens in a new tab)
MetaTotal electricity (TWh)202211.5sustainability.atmeta.com (opens in a new tab)
MetaTotal electricity (TWh)202315.3sustainability.atmeta.com (opens in a new tab)
MetaTotal electricity (TWh)202418.4sustainability.atmeta.com (opens in a new tab)

Methodology

We collect headline figures from the International Energy Agency, the Lawrence Berkeley National Laboratory report for the US Department of Energy, national statistics offices and company disclosures, and quote them as published with the year they refer to. Projections are labelled as projections.

Limits. Per-prompt energy figures are self-reported by companies, use different methods and cannot be compared directly. National figures cover all data centres, not only AI.

Data note. National figures are official statistics or government-commissioned studies and use different scopes and years. Per-prompt figures are self-reported by companies with different methods and are not directly comparable. Campus sizes are as announced; announced capacity is not the same as electricity use.

All 27 sources
  1. https://www.iea.org/reports/key-questions-on-energy-and-ai/executive-summary (opens in a new tab)
  2. https://www.energy.gov/articles/doe-releases-new-report-evaluating-increase-electricity-demand-data-centers (opens in a new tab)
  3. https://www.cso.ie/en/releasesandpublications/ep/p-dcmec/datacentresmeteredelectricityconsumption2025/keyfindings/ (opens in a new tab)
  4. https://restservice.epri.com/publicdownload/000000003002028905/0/Product (opens in a new tab)
  5. https://cloud.google.com/blog/products/infrastructure/measuring-the-environmental-impact-of-ai-inference (opens in a new tab)
  6. https://blog.samaltman.com/the-gentle-singularity (opens in a new tab)
  7. https://mistral.ai/news/our-contribution-to-a-global-environmental-standard-for-ai/ (opens in a new tab)
  8. https://sustainability.google/files/google-2026-environmental-report.pdf (opens in a new tab)
  9. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/2026-Microsoft-Environmental-Data-Fact-Sheet-PDF.pdf (opens in a new tab)
  10. https://sustainability.atmeta.com/wp-content/uploads/2025/10/Meta_2025-Environmental-Data-Index.pdf (opens in a new tab)
  11. https://www.iea.org/reports/energy-and-ai/energy-demand-from-ai (opens in a new tab)
  12. https://www.bundeswirtschaftsministerium.de/Redaktion/EN/Publikationen/Digitale-Welt/status-and-development-of-the-german-data-centre-landscape-executive-summary.pdf?__blob=publicationFile&v=2 (opens in a new tab)
  13. https://www.cbs.nl/en-gb/news/2025/51/data-centres-consume-4-6-percent-of-the-netherlands-electricity (opens in a new tab)
  14. https://assets.publishing.service.gov.uk/media/6a3ea4334c7605ab56723bfd/Data_centre_electricity_consumption_in_Great_Britain__2020_to_2024.pdf (opens in a new tab)
  15. https://www.nve.no/energi/energisystem/energibruk/energibruk-i-datasenter/ (opens in a new tab)
  16. https://www.mddi.gov.sg/newsroom/opening-by-sms-janil-puthucheary-at-atxsummit-digital-sustainability-forum/ (opens in a new tab)
  17. https://ens.dk/media/4384/download (opens in a new tab)
  18. https://openai.com/index/five-new-stargate-sites/ (opens in a new tab)
  19. https://techcrunch.com/2025/07/14/mark-zuckerberg-says-meta-is-building-a-5gw-ai-data-center/ (opens in a new tab)
  20. https://x.ai/colossus (opens in a new tab)
  21. https://blogs.microsoft.com/blog/2025/09/18/inside-the-worlds-most-powerful-ai-datacenter/ (opens in a new tab)
  22. https://blogs.microsoft.com/blog/2025/11/12/infinite-scale-the-architecture-behind-the-azure-ai-superfactory/ (opens in a new tab)
  23. https://www.cnbc.com/2025/10/29/amazon-opens-11-billion-ai-data-center-project-rainier-in-indiana.html (opens in a new tab)
  24. https://www.iea.org/reports/energy-and-ai/executive-summary (opens in a new tab)
  25. https://www.iea.org/reports/energy-and-ai/energy-supply-for-ai (opens in a new tab)
  26. https://www.occto.or.jp/assets/news/juyousoutei/260121_juyousoutei_r1.pdf (opens in a new tab)
  27. https://ember-energy.org/data/yearly-electricity-data/ (opens in a new tab)

Spotted an error or a missing row? Write to the newsroom via Contact. We correct and date every change.

How to cite or embed

Free to quote, chart and embed. Please credit i10X News and link to this page.